Hillsborough Street Construction Activities: Weeks of August 21- October 2 by NCSITE_Todd
September 24, 2009, 11:26 am
Filed under: Uncategorized

CONSTRUCTION UPDATE
During the weeks of September 21 – October 2, construction crews will be conducting the following activities:

  • Installation of sewer lines on the south side of Hillsborough Street starting at Chamberlain Street and heading west towards Horne and Pogue Streets;
  • Installation of the utility duct bank on the south side of Hillsborough Street starting at Logan Court and heading west towards Chamberlain and Horne Streets;
  • Installation of the utilities on Oberlin Road between Hillsborough Street and Pullen Road extension;
  • Installation of water lines on the south side of Hillsborough Street starting at Logan Court and heading west towards Chamberlain and Horne Streets;
  • Installation of brick sidewalk pavers on the south side on Hillsborough Street starting at Enterprise Street and heading west towards Logan Court and Chamberlain Street;
  • Installation of brick sidewalk pavers on the north side on Hillsborough Street between Oberlin and Pullen Roads;
  • Installation of curb and gutter and paving the south side of Hillsborough Street from Tompkins Hall heading west towards Horne Street; and
  • Grading and preparation of various sites for future construction activities.

Construction crews will be conducting the following night-time construction activities:

  • Installation of sewer lines and service crossing Hillsborough Street from the south side to businesses.

No weekend work is scheduled.

TRAFFIC UPDATE
Vehicles:
 Traffic delays on Hillsborough Street are expected between Oberlin Road and Enterprise Street.

Pedestrians:  Due to construction activities to install the brick sidewalk pavers, the Hillsborough Street entrance to Tompkins Hall will be closed during the two-week period and the entrance to Winston Hall will be closed periodically to safely facilitate project work.

In addition, the north side of Hillsborough Street between Oberlin Road and Maiden Lane will be closed to pedestrian activity as brick pavers are installed.  All through foot traffic will be diverted to the south side of Hillsborough Street, but access to Locopops and Red Hot + Blue will be maintained.



Hillsborough Street Construction Activities: Week of July 27-31 by NCSITE_Todd
July 23, 2009, 6:52 pm
Filed under: Uncategorized

During the week of July 27 through 31, construction crews will be conducting the following activities:

  • Electrical utility work by Progress Energy at Horne and Gardner Streets;
  • Installation of sewer lines on the south side of Hillsborough Street starting at Logan Court and heading west towards Chamberlain and Horne Streets;
  • Installation of the utility duct bank on the south side of Hillsborough Street starting at Enterprise Street and heading west towards Logan Court and Chamberlain Street;
  • Completion of  paving on Pullen Road Extension between Oberlin Road and Hillsborough Street.
  • Installation of water lines on the south side of Hillsborough Street starting at Maiden Lane and heading west towards Enterprise Street and Logan Court;
  • Installation of and brick sidewalk pavers and light pole bases around the Bell Tower on Pullen Road and on Hillsborough Street between Pullen and Oberlin Roads; and
  • Grading and preparation of various sites for future construction activities.

Construction crews will be conducting the following night-time construction activities:

  • Installation of conduit system and duct bank on the north side of Hillsborough at Enterprise Street from Gardner Street to Western Lanes Bowling Alley; and
  • Installation of sewer lines and service crossing Hillsborough Street from the south side to businesses over the course of the next 3 weeks.

Construction work on Pullen Road approaching Hillsborough Street may require detours around the Bell Tower along Watauga Club Drive.  Traffic delays are also expected between Oberlin Road and Enterprise Street due to intense construction activities in the area.

When paving is completed for Pullen Road Extension within the next few weeks, Oberlin Road traffic between Pullen Road Extension and Hillsborough Street will be diverted to the new route so construction activities can occur on Oberlin Road.

Thank you for your patience and understanding.