HILLSBOROUGH STREET CONSTRUCTION ACTIVITIES: WEEKS OF MARCH 15-28 by NCSITE_Todd
March 16, 2010, 2:10 pm
Filed under: Construction, Informational

Look up over the next two weeks and watch the utility poles and lines continue to come down along Hillsborough Street!!  In addition, utility construction on the south side of the street is nearly completed and crews are hard at work on the north side of Hillsborough Street.  

CONSTRUCTION UPDATE
During the weeks of March 15 to March 28, construction crews will be conducting the following activities:

  • Continued work on the Oberlin/Pullen and Hillsborough/Pullen roundabouts (March 15-19);
  • Laying of roof drains for businesses between Chamberlain and Horne Streets (2400 block; March 15-17)
  • Prep work for sidewalk construction on the south side of Hillsborough Street from Cox Avenue to Oberlin Road (1800 block; March 16-18);
  • Laying of conduit system to complete utility upgrades from Horne Street to Pogue Street (2500 block);
  • Final stages of installation of  brick sidewalk pavers, paving and street lights on the south side of Hillsborough Street from Horne Street to Gardner Street (2500-2600 blocks);
  • Prep work for sidewalk construction, installation of curb and gutter, and brick sidewalk pavers on the north side of Hillsborough Street from Logan Court to Horne Street (2300 & 2400 blocks);
  • Work to complete water and sewer service updates from Horne Street to Pogue Street (2500 block);
  • Prep work and removal of decommissioned overhead utility lines and poles along Hillsborough Street by Progress Energy; and
  • Grading and preparation of various sites for future construction activities.

TRAFFIC UPDATE
Vehicles: Minor traffic delays on Hillsborough Street are expected between Logan Court and Horne Street, with limited periods one-lane operations.

Temporary traffic delays at the intersection of Hillsborough Street and Pullen Road at times due to the movement of equipment for the island construction.

Horne and Lampe Street have been reopened to traffic.

The Oberlin Road parking lot for Locopops, Player’s Retreat and Sam & Bill’s remains open for customers.  Hillsborough Street (westbound) and Oberlin Road access (northbound) to BB&T remains open as well.

Limited on-street parking is available now on Hillsborough Street.  When traffic is shifted completely to the south side over the next two weeks, on-street parking will begin to become available on the south side of the street.

Pedestrians: Crosswalks and campus entrances remain open at Horne and Lampe Streets and at Gardner Street  in the busiest construction area. Numerous crosswalks are in place elsewhere along the street.

The sidewalks along the south side of Hillsborough Street beside NC State will be completed by the end of March.

Sidewalks on the north side of Hillsborough Street from Logan Court to Enterprise Street are closed due to construction activity. Pedestrian can use the completed sidewalks on the south side of Hillsborough Street in the area.

Sidewalks on the north side of Hillsborough Street from Jimmy Johns to Horne Street remain open but have been narrowed as crews work to demolish existing curb and gutter.  This narrowing will move west along the street as crews continue the work towards Garner Street.

EVENTS UPDATE
The Raleigh Rocks Half-Marathon and 5K will be taking place Saturday, March 27.  Hillsborough Street (NC State Fairgrounds to the Capitol Building) will be closed to vehicle traffic from early Saturday morning until approximately 2:00 pm.  For more information, go to http://www.ncraces.com/index.php?pr=Raleigh%20Rocks%20Half%20Marathon

See the previously posted project newsletter for details on our project progress, roundabout traffic patterns, and measures the construction crews will take to keep the sidewalks and doorways open when construction moves to the north side of the street.

Hillsborough Street businesses remain open for business. Please patronize your local businesses as we work to build the community’s new vision for Hillsborough Street.



HILLSBOROUGH STREET CONSTRUCTION ACTIVITIES: WEEK OF MARCH 8-14 by NCSITE_Todd
March 8, 2010, 11:06 am
Filed under: Construction, Informational

Look up over the next two weeks and watch the utility poles and lines start coming down along Hillsborough Street!!  In addition, utility construction on the south side of the street is nearly completed and crews are starting major work on the north side of Hillsborough Street.  

CONSTRUCTION UPDATE
During the weeks of March 5 to March 14, construction crews will be conducting the following activities:

  • Continued work on the Oberlin/Pullen roundabout;
  • Continued work on the Hillsborough/Pullen roundabout;
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the north side of Hillsborough Street from Enterprise Street to Logan Court (2200 block);
  • Final stages of installation of  paving and street lights on the south side of Hillsborough Street from Chamberlain Street heading west towards Horne Street (2400 block);
  • Installation of curb and gutter, brick sidewalk pavers, paving, and street lights on the south side of Hillsborough Street from Horne Street to Gardner Street (2500-2600 blocks);
  • Prep work for sidewalk construction (i.e. demolition of the existing curb & gutter, removal of tree grates,etc) on the north side of Hillsborough Street from Logan Court to Horne Street (2300-2400 blocks);
  • Prep work and removal of decommissioned overhead utility lines and poles along Hillsborough Street; and
  • Grading and preparation of various sites for future construction activities.

TRAFFIC UPDATE
Vehicles: Minor traffic delays on Hillsborough Street are expected between Chamberlain Street and Gardner Street, with limited periods one-lane operations.

Temporary traffic delays at the intersection of Hillsborough Street and Pullen Road at times due to the movement of equipment for the island construction.

Horne and Lampe Street have been reopened to traffic.

The Oberlin Road parking lot for Locopops, Player’s Retreat and Sam & Bill’s remains open for customers. Oberlin Road access to BB&T remains open as well.

Limited on-street parking is available now on Hillsborough Street.  When traffic is shifted completely to the south side over the next two weeks, on-street parking will be available on the south side of the street.

Pedestrians: Crosswalks and campus entrances remain open at Horne and Lampe Streets and at Gardner Street  in the busiest construction area. Numerous crosswalks are in place elsewhere along the street.

The sidewalks along the south side of Hillsborough Street beside NC State will be completed by the end of March.

Sidewalks on the north side of Hillsborough Street from Logan Court to Enterprise Street are closed due to construction activity. Pedestrian can use the completed sidewalks on the south side of Hillsborough Street in the area.

Sidewalks on the north side of Hillsborough Street from Jimmy Johns to Horne Street remain open but have been narrowed as crews work to demolish existing curb and gutter.  This narrowing will move west along the street as crews continue the work towards Garner Street.

EVENTS UPDATE
See the previously posted project newsletter for details on our project progress, roundabout traffic patterns, and measures the construction crews will take to keep the sidewalks and doorways open when construction moves to the north side of the street.

Hillsborough Street businesses remain open for business. Please patronize your local businesses as we work to build the community’s new vision for Hillsborough Street.



Hillsborough Street Construction Activities: Week of Feb. 22 – Mar 5 by NCSITE_Todd
February 19, 2010, 3:55 pm
Filed under: Construction

Construction on the south side of the street is finishing up and traffic will soon be switched to the south side for the whole corridor in early March.

CONSTRUCTION UPDATE
During the weeks of February 22 through March 5, construction crews will be conducting the following activities:

  • Continued work on the Oberlin/Pullen roundabout center island;
  • Continued work on the Hillsborough/Pullen roundabout center island;
  • Final stages of installation of sewer and water lines on the south side of Hillsborough Street starting at Pogue  Street heading west to Gardner Street (2600 block);
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the north side of Hillsborough Street from Enterprise Street to Logan Court (2200 block);
  • Final stages of installation of  brick sidewalk pavers and street lights on the north side of Hillsborough Street from Logan Court to Jimmy Johns (2300 – 2312 Hillsborough);
  • Final stages of installation of  brick sidewalk pavers, paving, and street lights on the south side of Hillsborough Street from Chamberlain Street heading west towards Horne Street (2400 block);
  • Installation of curb and gutter, brick sidewalk pavers, paving, and street lights on the south side of Hillsborough Street from Enterprise Street to Logan Court (2500-2600 blocks);
  • Work to remove decommissioned overhead utility lines and poles along Oberlin Road and Hillsborough Street;
  • Preparations for utility work and conduit system installation on the north side of Hillsborough Street near The Alley bowling alley (during spring break; 2500 block); and
  • Grading and preparation of various sites for future construction activities.

TRAFFIC UPDATE
Vehicles: Traffic delays on Hillsborough Street are expected between Chamberlain Street and Gardner Street, with limited periods one-lane operations.

Temporary traffic delays at the intersection of Hillsborough Street and Pullen Road at times due to the movement of equipment for the island construction.

Horne Street is now open to one-way traffic southbound, and Lampe Street will be open as construction crews move to the 2500 block for sidewalk construction (after paving and curb & gutter).

The Oberlin Road parking lot for Red Hot + Blue, Player’s Retreat, and Sam & Bill’s remains open for customers. Oberlin Road access to BB&T remains open as well.

Limited on-street parking is available now on Hillsborough Street.  When traffic is shifted south in March, on-street parking will be available on the south side of the street.

Pedestrians: Crosswalks and campus entrances remain open at Horne and Lampe Streets and at Gardner Street  in the busiest construction area. Numerous crosswalks are in place elsewhere along the street.

Sidewalks on the north side of Hillsborough Street from Logan Court to Enterprise Street are closed due to construction activity. Pedestrian can use the completed sidewalks on the south side of Hillsborough Street.

EVENTS UPDATE
See the previously posted project newsletter for details on our project progress, roundabout traffic patterns, and measures the construction crews will take to keep the sidewalks and doorways open when construction moves to the north side of the street.

Hillsborough Street businesses remain open for business. Please patronize your local businesses as we work to build the community’s new vision for Hillsborough Street.



Hillsborough Street Construction Activities: Week of Feb. 1-5 by NCSITE_Todd
January 29, 2010, 5:35 pm
Filed under: Construction

Construction on the center island for the Hillsborough Street roundabout continues and the first of the center brick medians have been going in as well.

CONSTRUCTION UPDATE
During the week of February 1 through 5, construction crews will be conducting the following activities:

  • Continued work on the Oberlin/Pullen roundabout center island;
  • Continued work on the Hillsborough/Pullen roundabout center island;
  • Installation of sewer and water lines on the south side of Hillsborough Street starting at Pogue  Street heading west to Gardner Street (2700 blocks), with some crossings across Hillsborough Street;
  • Installation of curb and gutter on Enterprise Street approach to Hillsborough Street;
  • Various utility work along Oberlin Road and the south side of Hillsborough Street;
  • Potential utility work and conduit system installation on the north side of Hillsborough Street near The Alley bowling alley (2600 block);
  • Continued median work from Oberlin Road to Enterprise Road;
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the south side of Hillsborough Street from Chamberlian Street heading west towards Horne Street (2300-2400 blocks); and
  • Grading and preparation of various sites for future construction activities.

TRAFFIC UPDATE
Vehicles: Traffic delays on Hillsborough Street are expected between Logan Court and Gardner Street, with one-lane operations at times.

Temporary traffic delays at the intersection of Hillsborough Street and Pullen Road at times due to the movement of equipment for the island construction.

Oberlin Road is now open to one-way traffic northbound.

The Oberlin Road parking lot for Red Hot + Blue, Player’s Retreat, and Sam & Bill’s remains open for customers. Oberlin Road access to BB&T remains open as well.

Horne and Lampe Streets approaching Hillsborough Street are closed due to utility construction work, but Horne Street is expected to open this week.

Pedestrians: Crosswalks and campus entrances remain open near Horne Street and the Alley (formerly Western Lanes) in the busiest construction area. Numerous crosswalks are in place elsewhere along the street.

Sidewalks on the north side of Hillsborough Street from Logan Court to Enterprise Street are closed due to construction activity. Pedestrian traffic will be shifted to the sidewalks on the south side of Hillsborough Street, now completed.

EVENTS UPDATE
Look for a project newsletter this week detailing our project progress, traffic patterns during the roundabout construction, and measures the construction crews will take to keep the sidewalks and doorways open during when construction moves to the north side of the street.

Hillsborough Street businesses remain open for business. Please patronize your local businesses as we work to build the community’s new vision for Hillsborough Street.

Remember that the Krispy Kreme Challenge is on Feb. 6. Runners will assemble on the 2100 block of Hillsborough Street.  Pullen Street will be closed from the roundabout one block off Hillsborough to Hillsborough from ~7:30 to 11 a.m. on Feb. 6.  Hillsborough Street will be closed from Enterprise to Woodburn and Boylan to Woodburn from 8 a.m. to 11 a.m.  St Mary’s Street closed from Peace to Hillsborough St from 8:15 a.m. to 10:30 a.m.   The race should be over and all traffic will be reopened by 11 a.m. on Saturday.



Hillsborough Street Construction Activities: Weeks of Dec. 14 – Jan. 1 by NCSITE_Todd
December 17, 2009, 7:07 pm
Filed under: Construction
 
CONSTRUCTION UPDATE
During the weeks of  December 13 – January 1, construction crews will be conducting the following activities:
  • Installation of the Oberlin/Pullen roundabout center island;
  • Installation of the Hillsborough/Pullen roundabout center island;
  • Installation of sewer and water lines on the south side of Hillsborough Street starting at Horne Street and heading west to Gardner Street (2500-2600 blocks), with some crossings across Hillsbrough Street;
  • Installation of curb and gutter on Enterprise Street approach to Hillsborough Street;
  • Installation of conduit systems on the north side of Hillsborough Street near Sylvas Pizza (2400 block) and The Alley bowling alley (2600 block);
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the south side of Hillsborough Street  from Logan Court heading west towards Horne Street (2300-2400 blocks);
  • Finishing the installation of brick sidewalk pavers on the north side of Hillsborough Street from Enterprise Street heading east towards Maiden Lane and Pullen Road (1900-2000 blocks);
  • Paving on Oberlin Road between Hillsborough Street and Pullen Road extension (if weather permits);
  • Removal of temporary traffic signals and installation of permanent traffic signals and mast arms; and
  • Grading and preparation of various sites for future construction activities.

Crews will be off Chirstmas Eve and Day as well as New Years Day.

TRAFFIC UPDATE
Vehicles:
 Traffic delays on Hillsborough Street are expected between Logan Court and Gardner Street, with one-lane operations at times.

Traffic delays on Oberlin Road are expected between Clark Avenue and Hillsborough Street at times due to the island construction and concrete truck traffic.

Construction on the center island for the Hillsborough Street roundabout began ahead of schedule during the week of Christmas.  Be on the look out for a project newsletter in January detailing our project progress, traffic patterns during the roundabout construction, and measures the construction crews will take to keep the sidewalks and doorways open during when construction moves to the north side of the street.

The Oberlin Road parking lot for Red Hot + Blue, Player’s Retreat, and Sam & Bill’s remains open for customers.  Oberlin Road access to BB&T remains open as well.

Oberlin Road is now open to one-way traffic northbound.

Horne Street approaching Hillsborough Street is closed due to utility construction work.

Pedestrians:  Crosswalks and campus entrances remain open  near  Horne Street and the Alley (formerly Western Lanes) in the busiest construction area.  Numerous crosswalks are in place elsewhere along the street.

Pedestrians and customers can still access Oberlin Road businesses during the construction process, as see the new wider sidewalks along the street on the business side.

Sidewalks on the north side of Hillsborough Street from Logan Court to Maiden Lane will be closed and pedestrian traffic will be shifted to the sidewalks on the south side of Hillsborough Street, now completed.

EVENTS UPDATE
Hillsborough Street businesses remain open for business.  Please patronize your local businesses as we work to build a new vision for Hillsborough Street.



Hillsborough Street Construction Activities: Weeks of Nov. 30 – Dec. 13 by NCSITE_Todd
December 3, 2009, 9:53 am
Filed under: Construction
 
CONSTRUCTION UPDATE
During the weeks of November 30 – December 13, construction crews will be conducting the following activities:
  • Installation of sewer and water lines on the south side of Hillsborough Street starting at Horne Street and heading west to Gardner Street (2500-2600 blocks);
  • Installation of storm drainage systems on the north side of Hillsborough Street near Logan Court;
  • Installation of utility duct bank  and electrical service manholes across Hillsborough Street at Horne Street and along Horne Street;
  • Installation of curb and gutter on Enterprise Street approach to Hillsborough Street;
  • Installation of conduit systems on the north side of Hillsborough Street between Logan Court and Chamberlain Street (2300 block);
  • Work to complete sewer service on Horne Street (starting Wednesday 12/2);
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the south side of Hillsborough Street  from Logan Court heading west towards Horne Street (2300-2400 blocks);
  • Installation of brick sidewalk pavers on the north side of Hillsborough Street from Enterprise Street heading east towards Maiden Lane and Pullen Road (1900-2000 blocks);
  • Paving on Oberlin Road between Hillsborough Street and Pullen Road extension; and
  • Grading and preparation of various sites for future construction activities.

Crews will be working this weekend on Saturday December 5, conducting the following activities:

  • Installation of sewer and water lines on the south side of Hillsborough Street starting at Horne Street and heading west to Gardner Street (2500-2600 blocks);
  • Work to complete sewer service on Horne Street and on Oberlin Road; and,
  • Installation of utility duct bank across Hillsborough Street at Horne Street.

TRAFFIC UPDATE
Vehicles:
 Traffic delays on Hillsborough Street are expected between Oberlin Road and Horne Street.

The Oberlin Road parking lot for Red Hot + Blue, Player’s Retreat, and Sam & Bill’s remains open for customers.

Pedestrians:  New crosswalks and campus entrances have been near Frazier’s Bistro, Horne Street, and the Alley (formerly Western Lanes).

Pedestrians and customers can still access Oberlin Road businesses during the construction process, as see the new wider sidewalks along the street on the business side.

Sidewalks on the north side of Hillsborough Street from Logan Court to Maiden Lane will be closed and pedestrian traffic will be shifted to the sidewalks on the south side of Hillsborough Street, now completed.

EVENTS UPDATE
Hillsborough Street businesses remain open for business.  Please patronize your local businesses as we work to build a new vision for Hillsborough Street.



Hillsborough Street Construction Activities: Week of Nov. 23-27 by NCSITE_Todd
November 23, 2009, 2:57 pm
Filed under: Construction
Please excuse our absence, but our contractors have been so busy working on Hillsborough Street, they haven’t had time to update us on their status.
 
CONSTRUCTION UPDATE
During the week of November 23-27, construction crews will be conducting the following activities:
  • Installation of sewer and water lines and storm drainage systems on the south side of Hillsborough Street starting at Horne Street and heading west to Gardner Street (2500-2600 blocks);
  • Installation of curb and gutter, brick sidewalk pavers, and paving on the south side of Hillsborough Street  from Chamberlain Drive heading west towards Pogue Street (2400-2500 blocks);
  • Installation of curb and gutter and brick sidewalk pavers on the north side of Hillsborough Street from Enterprise Street heading east towards Maiden Lane and Pullen Road (1900-2000 blocks);
  • Installation of temporary street lights;
  • Installation of curb and gutter and paving on Oberlin Road between Hillsborough Street and Pullen Road extension; and
  • Grading and preparation of various sites for future construction activities.

No weekend or night work is scheduled, and construction crews will be off on Thursday to celebrate the Thansgiving holiday.

TRAFFIC UPDATE
Vehicles:
 Traffic delays on Hillsborough Street are expected between Oberlin Road and Enterprise Street.

The Oberlin Road parking lot for Red Hot + Blue, Player’s Retreat, and Sam & Bill’s remains open for customers.  Groveland Avenue will be closed temporarily as construction activities on Oberlin Road are finished up.

Pedestrians:  New crosswalks and campus entrances have been near Frazier’s Bistro, Horne Street, and the Alley (formerly Western Lanes).

Pedestrians and customers can still access Oberlin Road businesses during the construction process.

Sidewalks on the north side of Hillsborough Street from Logan Court to Maiden Lane will be closed and pedestrian traffic will be shifted to the sidewalks on the south side of Hillsborough Street, now completed.

EVENTS UPDATE
No event updates