Hillsborough Street Roundabouts


Hillsborough Street Construction Activities: Week of June 8-12 by NCSITE_Todd
June 5, 2009, 1:42 pm
Filed under: Construction

During the week of June 8 through 12, construction crews will be conducting the following activities during daytime hours:

  • Installing duct bank for underground utilities on the south side of Hillsborough Street between Gardner and Pogue Streets;
  • Installing sewer lines between the south side of Hillsborough Street and the Court of the Carolinas near Tompkins Hall;
  • Installing water lines, sewer lines, and the utility duct bank on the south side of Hillsborough Street from Tompkins Hall to Logan Street;  and
  • Installing storm drains along Pullen Road and the future Pullen Road extension, from the south side of Hillsborough Street north to Oberlin Road.

Construction crews will be conducting nighttime construction near the Hillsborough Street intersections at Pullen Road, including:

  • Installing manholes and sewer lines near the Wardlaw Building and along Ferndell Lane.
Advertisements

Leave a Comment so far
Leave a comment



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s



%d bloggers like this: