During the week of June 1 through 5, construction crews will be conducting the following activities during daytime hours:

  • Installing block walls in the basement of Red, Hot, & Blue restaurant;
  • Installing duct bank for underground utilities on the south side of Hillsborough Street between Gardner and Pogue Streets;
  • Excavating and preparing to install water and sewer lines between the south side of Hillsborough Street and the Court of the Carolinas near Tompkins Hall;
  • Installing water lines, sewer lines, and the utility duct bank on the south side of Hillsborough Street, starting near Tompkins Hall and heading west towards Gardner Street;  and
  • Installing storm drains along Pullen Road and the future Pullen Road extension, from the south side of Hillsborough Street north to Oberlin Road.

Construction crews will be conducting nighttime construction near the Hillsborough Street intersections at Pullen and Oberlin Roads, including:

  • Installing manholes and sewer lines starting at the Hillsborough/Oberlin intersection, moving west to Pullen Road and the Wardlaw Building, and then north along Ferndell Lane.

Hillsborough Street should remain open to traffic during these nighttime activities, but be aware that crews may need to temporarily close Hillsborough Street between Oberlin and Pullen Roads or Ferndell Lane during the work.

Advertisements

Leave a Comment so far
Leave a comment



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s



%d bloggers like this: