During the week of May 25th through 29th, construction crews will be conducting the following activities:

  • Installing underground pipes and ducts for utilities on the south side of Hillsborough Street near Gardner and Pogue Streets;
  • Excavating and preparing to install water and sewer lines on the south side of Hillsborough Street and in the Court of the Carolinas near Tompkins Hall;
  • Installing conduit on the south side of Hillsborough Street between Oberlin and Pullen Roads near the Chancellor’s House; and
  • Grading at various locations on Hillsborough Street.
Advertisements

Leave a Comment so far
Leave a comment



Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s



%d bloggers like this: